M205 Carlton Water Main Renewal Project

 

This project is an essential upgrade to ensure safe and secure water supply for Carlton, Carlton North and the inner city for years to come.

The project includes installing 2.3km of new pipe along Canning Street, between Faraday Street and Park Street. Construction works started in August 2019 and are anticipated to be completed in mid-2020.

Project Update 26 February 2020

The M205 project team has installed 1.3km of new water main pipe along Canning Street, Carlton and Carlton North with approximately 1km remaining. The stage 5 trenching works are currently located in the section between Fenwick and Richardson Streets., Carlton North

The stage 4 bore works at the intersection of Canning and Princes St are now in the final stages. The Micro Tunneling Bore Machine (MTBM) has completed tunneling underneath Princes Street and has now been removed via the retrieval shaft located at the northern side of the intersection. The new pipe is being fed through and will then be connected to the rest of the pipeline.

Upcoming works

The stage 4 works at the intersection of Canning and Princes streets are expected to be completed by the end of March. These works will include installing the pipe into the underground bore tunnel, backfilling the launch shaft and the retrieval shaft, and connecting the pipe to the already installed pipeline. This will require some additional trenching works from Princes to Davis street. This area will then be reinstated and returned to the community.

Stage 5 works will continue trenching north on Canning Street and are expected to reach Park Street in early April 2020.

Current detour route

Southbound bicycle riders on Canning Street will be detoured around the construction site, turning right onto Park Street then left onto Rathdowne Street. Bicycle riders can then continue south towards the city on Rathdowne Street or turn left at Kay Street to return to Canning Street.

Northbound riders can continue to use Canning Street as normal, with no changes to this route.

To ensure your own safety, and that of pedestrians and our construction team, we ask that people who choose to ride on Canning Street please avoid riding on the wrong side of the road, or on footpaths. We recommend following the detour route or walking your bike past the construction site.

Richardson detour

City West Water has established a Community Reference Group (CRG) in Carlton/Carlton North as a way to share information with the community about construction impacts, answer questions on construction activities, and contribute to the community project.

M205 Community Projects

City West Water has committed to delivering value to our customers through a community project, or community projects that will enhance the liveability of the area.

What work are we undertaking?

City West Water (CWW) is replacing a 2.3km section of water main pipe that provides water to Carlton, Carlton North and the Inner City. The current pipe runs under Nicholson Street and is almost 140 years old and needs to be replaced. The new main will be relocated to Canning Street with a pipe almost double in size to meet future capacity needs as our city grows.

Who is undertaking the work?

City West Water is working with Jaydo as its construction partner to deliver the M205 Renewal Project.

What to expect

Work hours will be Monday to Friday between 7am and 6pm and Saturday between 9am and 3pm, when required.

Impacts during the project are expected to include temporary road closures, temporary reduction of on-street parking, changes to private property access, noise, dust and vibration from construction activity.

To minimise impacts, work will be carried out in sections and each area reinstated when works move on to the next section.

Safety is a key priority. During construction, the work site will be fenced off with temporary fencing. Traffic controllers will be onsite to help road users and pedestrians navigate the area safely. Southbound bicycle riders will need be detoured around the temporary road closures for safety.

We will work closely with Yarra City Council, Melbourne City Council, Bicycle Network Victoria, residents, traders and other key user groups to identify and manage impacts.

We will provide you with regular updates and advanced notice prior to road and property access changes.

Where are the works?

The work will generally be carried out in the southbound lane of Canning Street , and a small section of Park Street and Nicholson Street. The works will be carried out in sections, the map below shows where we will be working during each stage of the project.

update new map

What is the timeline?

Construction started August 2019 and will finish mid-2020.

Stage Estimated timing Description
Project announcement 15 February 2019 Share project information with stakeholders and community and introduce Jaydo as our project construction partner.
Site investigations February to July 2019 Understanding ground conditions, surveying and locating electronic services to inform functional design.
Community and stakeholder engagement Commence February and is ongoing Working with all stakeholders and community throughout the planning, construction and reinstatement stages to keep you informed and minimise impact. Feedback about construction impacts and community projects will be considered as part of the project’s planning process.
Community Reference Group June 2019 The Community Reference Group had its first meeting 20 June 2019.
Community Projects July 2019 Customers contribute ideas for the community projects.
Functional designs February to July 2019 Finalise the design and update community and stakeholders.
Site mobilisation 12 August 2019 Set-up off site offices
Machinery and equipment delivered to site
Construction starts 19 August 2019 Main construction activity.
Community projects October 2019 Update on community projects to be short listed.
Construction complete Mid 2020 Project completion:
pack up construction site and 
final reinstate to its pre-existing condition, prior to the works taking place.

How to stay informed about the project.

Sign up for project email updates.

For general enquiries please contact:

Our project number on 1300 105 041, email M205@citywestwater.com.au or stop in to speak with our project team at the Project Information Centre located at 326 Park Street, Carlton North.

FAQs

Will there be any impact on my water supply?

It is not expected that any service interruptions will occur, however should we need to interrupt your service, we will contact you beforehand.

What construction impacts can I expect?

There will be localised impacts such as noise, dust and vibrations. The construction team will manage noise from equipment such as generators and power tools by operating within Environment Protection Authority (EPA) decibel limits. Works will be limited to EPA guideline hours only.

Mesh fencing around the construction site will minimise dust generated by activities such as drilling and excavating. To assist with keeping the construction dust out of residences and buildings, we suggest that you keep your front windows and doors closed where possible during times of peak construction. Levels of vibrations will be monitored during these activities. However, if you have any concerns about the level of vibration you are experiencing, please contact the project team.

To avoid major impacts where Canning Street intersects with Elgin and Princes streets, we will be tunnelling underneath the road using a Micro Tunnelling Boring Machine (MTBM)

Why does CWW need to renew this water main?

The pipeline currently in Nicholson Street was installed almost 140 years ago and is nearing the end of its design life. The new pipe needs to be installed to ensure the community continues to receive clean drinking water. The new pipe will also be larger in diameter to meet the growing needs of the community into the future.

Why can’t CWW just fix the existing water main? Or just fix the parts that are leaking?

The current cast iron pipe was laid some 140 years ago has serviced the community well but has now deteriorated and has come to the end of its design life. This results in leaks and a high potential for failure which will have a huge impact on the community. The pipe also needs to be relocated as the upcoming installation of the Yarra Trams super stops on Nicholson Street will make it very hard to access the pipe for maintenance and repair.

The new pipe will be almost double in size and meet the current and future needs of a growing Melbourne for the next 140 years.

Who decided where the new pipe will go and how was this decision made?

City West Water engaged KBR to undertake an independently led analysis using a Multi Criteria Analysis (MCA) to review options based on many factors such as community, impacts, future needs, and available resources.

A MCA is a structured framework that investigates, analyses and suggests possible options to resolve complex decisions beyond looking at solutions based on monetary value.

As the MCA is independently led, the results of the analysis can provide confidence that all factors are considered in a methodological manner without bias. CWW also sought the input from subject matter experts such as local government, other water and infrastructure authorities and construction companies and arborists.

The new pipe will be almost double in size and meet the current and future needs of a growing Melbourne for the next 140 years

There is so much work going on in our area, why do you have to do this now?

We understand there is a lot of work happening in the local area. This is due to increases in development and population as well as aging infrastructure that needs upgrading. We need to do this project now due to the condition of the pipe to ensure you have access to clean drinking water. The pipe also needs to be relocated due to the upcoming installation of tram super stops along Nicholson Street, which will make it very hard to access the pipe for maintenance and repair.

What are the impacts to parking?

There will be parking changes along the alignment. When working in local streets residents are required to park their cars outside of this area to ensure a safe working zone. We will work with residents near work areas to maintain pedestrian access to private property and open up areas when it is safe to do so.

Residents who are required to relocate their car will be provided with direct notification. All parking permit holders within the Canning Street area will be able to park anywhere within their allocated zones during this time.

How will I safely move around the site?

Traffic diversions are necessary to ensure the safety of all road users. We understand this may cause an inconvenience to people who choose to ride their bikes on Canning Street and we appreciate your patience and cooperation during this time. Our Traffic Management Plans take into account all road users and will utilise a number of methods to ensure ease of access and safety. This includes information distribution through bicycle groups, signage, traffic management controllers and bicycle diversion plans if applicable.

Pedestrian access around the work site will be maintained throughout the project.

What if I ride to work via Canning Street?

If you use Canning Street to ride to work, you will have the option of:

  • Continuing to ride your bike on Canning Street and using the signed detour around the section closed for works, or;
  • Choosing an alternative street, such as Rathdowne, Drummond or Station Street to avoid the isolated temporary road closures along Canning St. This option will be better suited to bike riders when we are delivering works between Park and Princes Street from late 2019

Local closures and detours will only affect southbound riders heading towards the city. All northbound cyclists can continue to use Canning Street as usual normal.

Please tell us what you think.
If you require a response, please Contact us.