In December 2018, we completed essential works in your neighbourhood to prevent a sewer spill.
Project Update: 13 May 2019
We are undertaking works on a section of sewer on Alexandra Parade between Brunswick and Napier Streets. Last night there was a complication with the works which means we need to keep one lane of traffic closed throughout the day today in order to monitor the sewer.
Works will recommence tonight which we anticipate will resolve the issue. We will then continue with the works as planned this week. At this point our works schedule does not include further impacts to peak hour traffic after today.
The bypass sewer pump (City West Water Pump Site) located on Napier Street may be required to be operational during these times. There will be some noise associated with this activity as generators will be used.
We have notified nearby residents and will continue to do so if there any changes to the work schedule that may impact them. We sincerely apologise to any motorists who have been impacted by today’s traffic delays on Alexandra Parade.
Current schedule of night works
- Works will take place during the night on Monday 13 May until Friday 17 May, 8.00pm to 5.00am on Alexandra Parade and the corner of Brunswick Street.
- Bypass sewer pump (City West Water Pump Site) on Napier Street may be required to be operational during these times and will be largely silent with acoustic draping.